Easebourne Parish Council received the following update from West Sussex Highways this morning –

I can confirm that the stone for North Mill Bridge is being delivered to site today and the concrete barriers will be moved overnight to provide the necessary working room for the stonemason.  We anticipate the work will be completed towards the end of next week. Once the bridge repairs have been carried out the lining work on the road itself will be undertaken overnight and the lights will be removed from site.