Another busy and successful week on site at Easebourne Park

Another busy and successful week on site at Easebourne Park, with the traditional play equipment on track to be completed by this weekend.  We then welcome back PB Groundworks who will start creating the 650m of meandering pathways on 6th August. The Park is really starting to look complete now; however, the signage, rubbish bins, dog bag dispensers and park benches still to be fitted.  All on track for completion and the official opening on the 1st September!